V2504 ARMSTRONG CREEK TOWN CENTRE - Offentlig prosjektsted
-
16th oktober 2025, Daily Pre-Start Thursday 16/10
Crane Stage 2 Steel
Crane E Store
Sth Carpark
Mid Car Park sewer -
22nd september 2025, Safety - Elevated Work Platforms
The Safety Observer Due to the importance of a prompt rescue, EWP operators should never operate an EWP alone. A safety observer should be appointed to warn the operator(s) of hazards and ensure prompt action to rescue the operator(s). The safety observer:
must be trained in the operation of the EWP and licensed where required under the legislation for the type of EWP being operated
needs to have a line of sight to the operator
needs to be trained in the emergency procedures for that specific EWP
should not leave the area until the EWP is lowered to a stowed position and the operator has alighted from the platform
Vær på anleggsted
Sist oppdatert kl.: 19:21
Temperatur: 18C (App 14C)
Vindfart: 26KMH
Maks. Vind: 30KMH @16:21
Regn side 09.00: 0,0mm
Min. temperatur: 18C @19:14
Maks. temperatur: 38C @14:04 27.01.2026
Vindkast: 32KMH
Maks. vindkast: 35KMH @14:31
Observasjonssted - Geelong Racecourse, VICTORIA
Tidssone - austaustralsk standardtid
Værmelding – onsdag, 28 januar
Partly cloudy.
Min.: 15C Maks.: 24C
Sjanse for regn: 10%
Sted for værmelding – Geelong, VICTORIA
Tidssone - austaustralsk standardtid
I morgen - torsdag, 29 januar
Partly cloudy.
Min.: 17C Maks.: 28C
Sjanse for regn: 20%
-
South Australian Environment Protection Act 1993 current at 20251215
Lastet opp 15.12.2025
save_alt Last ned -
modelcop_managing-risks-respirable-crystalline-silica_nov2025
Lastet opp 10.12.2025
save_alt Last ned -
model_code_of_practice_-_managing_psychosocial_hazards_at_work_25082022_0
Lastet opp 10.12.2025
save_alt Last ned -
Draft-Code-of-Practice_-Preparation-of-safety-data-sheets-for-hazardous-chemicals
Lastet opp 10.12.2025
save_alt Last ned -
Draft-Code-of-Practice_-Managing-risks-of-hazardous-chemicals-in-the-workplace
Lastet opp 10.12.2025
save_alt Last ned -
Draft-Code-of-Practice_-Labelling-of-workplace-hazardous-chemicals
Lastet opp 10.12.2025
save_alt Last ned -
Draft-Code-of-Pracitce_-How-to-manage-and-control-asbestos-in-the-workplace
Lastet opp 10.12.2025
save_alt Last ned -
codeofpractice_precasttiltupandconcreteelementsbuildingconstruction_2008_pdf
Lastet opp 10.12.2025
save_alt Last ned -
Code-of-Practice_-Managing-noise-and-preventing-hearing-loss-at-work
Lastet opp 10.12.2025
save_alt Last ned -
V2504 ARMSTRONG CREEK SITE SPECIFIC INDUCTION QUESTIONNAIRE ONLY
Lastet opp 01.07.2025
save_alt Last ned -
Generated_VIC-24-SWMS-Patching_levelling_and_grinding_of_concrete
Lastet opp 30.06.2025
save_alt Last ned
Vet du om PVU-kravene for dette anlegget?
Sørg for at du har riktig sikkerhetsutstyr for den første dagen på anleggsplassen.
Kom i gang med arbeidet tidligere når du ankommer anleggsplassen.
Fullfør nettstedsregistreringen din online når det passer deg og spar tid.
Vet du om PVU-kravene for dette anlegget?
Sørg for at du har riktig sikkerhetsutstyr for den første dagen på anleggsplassen.
Kom i gang med arbeidet tidligere når du ankommer anleggsplassen.
Fullfør nettstedsregistreringen din online når det passer deg og spar tid.