16th October 2025, Daily Pre-Start Thursday 16/10
Crane Stage 2 Steel
Crane E Store
Sth Carpark
Mid Car Park sewer -
22nd September 2025, Safety - Elevated Work Platforms
The Safety Observer Due to the importance of a prompt rescue, EWP operators should never operate an EWP alone. A safety observer should be appointed to warn the operator(s) of hazards and ensure prompt action to rescue the operator(s). The safety observer:
must be trained in the operation of the EWP and licensed where required under the legislation for the type of EWP being operated
needs to have a line of sight to the operator
needs to be trained in the emergency procedures for that specific EWP
should not leave the area until the EWP is lowered to a stowed position and the operator has alighted from the platform
Current Site Weather
Last Updated at: 7:21 PM
Temperature: 65F / 18C (App 58F / 14C)
Wind Speed: 16MPH
Max. Wind: 19MPH @4:21 PM
Rain since 9AM: 0.0in
Min Temp: 64F / 18C @7:14 PM
Max Temp: 101F / 38C @2:04 PM 1/27/2026
Gust: 20MPH
Max Gust: 22MPH @2:31 PM
Observation Location - Geelong Racecourse, VICTORIA
Time Zone - Australian Eastern Standard Time
Forecast - Wednesday, 28 January
Partly cloudy.
Min: 59F / 15C Max: 75F / 24C
Chance of Rain: 10%
Forecast Location - Geelong, VICTORIA
Time Zone - Australian Eastern Standard Time
Tomorrow - Thursday, 29 January
Partly cloudy.
Min: 63F / 17C Max: 82F / 28C
Chance of Rain: 20%
-
South Australian Environment Protection Act 1993 current at 20251215
Uploaded 12/15/2025
save_alt Download -
model_code_of_practice_-_managing_psychosocial_hazards_at_work_25082022_0
Uploaded 12/10/2025
save_alt Download -
Draft-Code-of-Practice_-Preparation-of-safety-data-sheets-for-hazardous-chemicals
Uploaded 12/10/2025
save_alt Download -
Draft-Code-of-Practice_-Managing-risks-of-hazardous-chemicals-in-the-workplace
Uploaded 12/10/2025
save_alt Download -
Draft-Code-of-Practice_-Labelling-of-workplace-hazardous-chemicals
Uploaded 12/10/2025
save_alt Download -
Draft-Code-of-Pracitce_-How-to-manage-and-control-asbestos-in-the-workplace
Uploaded 12/10/2025
save_alt Download -
codeofpractice_precasttiltupandconcreteelementsbuildingconstruction_2008_pdf
Uploaded 12/10/2025
save_alt Download -
Code-of-Practice_-Managing-noise-and-preventing-hearing-loss-at-work
Uploaded 12/10/2025
save_alt Download -
V2504 ARMSTRONG CREEK SITE SPECIFIC INDUCTION QUESTIONNAIRE ONLY
Uploaded 7/1/2025
save_alt Download -
Generated_VIC-24-SWMS-Patching_levelling_and_grinding_of_concrete
Uploaded 6/30/2025
save_alt Download
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enroll online at your convenience and save yourself time.
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Enroll online at your convenience and save yourself time.